Waste Water Collection System Rehabilitation
Federal contribution
$600,000
Federal share33%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedJan 27, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Saskatoon
- Construction start
- Mar 3, 2010(actual)
- Construction end
- Oct 31, 2011(actual)