Route 245 - Minor Collector Highway

Antigonish, Nova Scotia

completeHighways and RoadsISF
Federal contribution
$1.1M
$1,106,230
Federal share50%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 30, 2009
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Nova Scotia
Construction start
Jul 27, 2009(actual)
Construction end
Oct 20, 2009(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 1, 2009