Water Distribution-Watermain Renewal - Phase 2

Saskatoon, Saskatchewan

completeDrinking WaterISF
Federal contribution
$560,720
Federal share22%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 24, 2009
ApprovedJan 27, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Saskatoon
Construction start
May 4, 2010(actual)
Construction end
Sep 15, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Mar 29, 2010
  • Construction end7 weeks lateforecast Jul 31, 2011

Also in Saskatoon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29047 in the federal list. How to read these figures.