St. Johns Kelley Drive/Everard Drive Sewer Replacement
St. John's, Newfoundland and Labrador
Federal contribution
$200,000
Federal share33%
of $600.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 11, 2009
ApprovedMay 26, 2009
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of St. John's
- Construction start
- Jun 1, 2009(actual)
- Construction end
- Sep 30, 2009(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Jul 1, 2009
- Construction end13 months earlyforecast Oct 31, 2010