2025 Canada Summer Games Track and Field Facility
St. John's, Newfoundland and Labrador
Federal contribution
$11.6M
$11,596,522
Federal share33%
of $34.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 17, 2022
202320242025
Built
Approved 4 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Government of Newfoundland and Labrador
- Construction start
- May 1, 2023(actual)
- Construction end
- Jul 2, 2025(actual)
Against the original forecast
- Construction start4 months lateforecast Jan 9, 2023
- Construction end5 weeks lateforecast May 31, 2025