2025 Canada Summer Games Track and Field Facility

St. John's, Newfoundland and Labrador

completeRecreationCCRIS
Federal contribution
$11.6M
$11,596,522
Federal share33%

of $34.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 17, 2022
202320242025
Built

Approved 4 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
May 1, 2023(actual)
Construction end
Jul 2, 2025(actual)

Against the original forecast

  • Construction start4 months lateforecast Jan 9, 2023
  • Construction end5 weeks lateforecast May 31, 2025

Also in St. John's

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65350 in the federal list. How to read these figures.