Road Rehabilitation on Route 1 - Trans-Canada Highway and Route 2 - Pitts Memorial Drive
St. John's, Newfoundland and Labrador
Federal contribution
$9.1M
$9,140,410
Federal share50%
of $18.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2016
20172018
Built
Approved 5 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Construction start
- Sep 20, 2016(actual)
- Construction end
- Sep 30, 2018(actual)
Against the original forecast
- Construction start7 weeks lateforecast Aug 1, 2016
- Construction end2 months lateforecast Jul 31, 2018
Also in St. John's
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46832 in the federal list. How to read these figures.