St. Johns Forest Road Watermain Upgrade
St. John's, Newfoundland and Labrador
Federal contribution
$816,667
Federal share33%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 11, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of St. John's
- Construction start
- Jul 30, 2010(actual)
- Construction end
- Sep 11, 2011(actual)
Against the original forecast
- Construction end3 weeks earlyforecast Sep 30, 2011
Also in St. John's
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29085 in the federal list. How to read these figures.