Back to projects

Charlottetown Perimeter Highway - Phase 2

Charlottetown, Prince Edward Island

completeHighways and RoadsISF
Federal contribution
$3.3M
$3,250,000
Federal share50%

of $6.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Construction start
May 25, 2010(actual)
Construction end
Mar 30, 2011(actual)