Construction of the Rivière-du-Loup Music School

Rivière-du-Loup, Quebec

completeCultureISF
Federal contribution
$1.0M
$1,036,597
Federal share29%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 16, 2010(actual)
Construction end
Feb 25, 2011(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 28, 2010

Also in Rivière-du-Loup

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29205 in the federal list. How to read these figures.