Pointe de Rivière-du-Loup Maritime Park
Federal contribution
$2.7M
$2,671,182
Federal share33%
of $8.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2017
today
20182020202220242026
BuiltForecast
Approved 2 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Rivière-du-Loup
- Construction start
- Dec 31, 2025(forecast)
- Construction end
- Aug 31, 2026(forecast)
Also in Rivière-du-Loup
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51697 in the federal list. How to read these figures.