Back to projects

Highway 20 Resurfacing

Saint-Louis-de-Blandford, Quebec

completeHighways and RoadsISF
Federal contribution
$1.6M
$1,617,500
Federal share50%

of $3.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Sep 27, 2010(actual)
Construction end
Jun 30, 2011(actual)

Against the original forecast

  • Construction end3 months lateforecast Mar 31, 2011

Also in Saint-Louis-de-Blandford