Multipurpose recreation centre

Saint-Louis-de-Blandford, Quebec

completeRecreationCC Top Up
Federal contribution
$257,984
Federal share33%

of $774.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 2, 2010
2011
Built

Approved 5 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Construction start
Apr 30, 2010(actual)
Construction end
Jun 30, 2011(actual)

Against the original forecast

  • Construction end4 months earlyforecast Oct 31, 2011

Also in Saint-Louis-de-Blandford