Route 11 - Neguac to Route 455

Neguac, New Brunswick

completeHighways and RoadsISF
Federal contribution
$693,000
Federal share50%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 12, 2009
ApprovedJul 28, 2010
2010
Built

Approved 14 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of New Brunswick
Construction start
Sep 14, 2009(actual)
Construction end
Oct 16, 2009(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 31, 2009
  • Construction end2 weeks earlyforecast Oct 31, 2009