Sanitary sewer extension in six streets

Neguac, New Brunswick

completeWastewaterCWWF
Federal contribution
$1.2M
$1,165,912
Federal share50%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 18, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Neguac
Construction start
May 21, 2017(actual)
Construction end
Dec 5, 2017(actual)

Against the original forecast

  • Construction end22 months earlyforecast Sep 30, 2019

Also in Neguac

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47320 in the federal list. How to read these figures.