Back to projects

Grosse Isle Street Paving

Rosser, Manitoba

completeHighways and RoadsISF
Federal contribution
$84,029
Federal share28%

of $303.6K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 11, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 16, 2010(actual)
Construction end
May 25, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Aug 1, 2010
  • Construction end2 months earlyforecast Jul 31, 2011

Also in Rosser

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29244 in the federal list. How to read these figures.