National Highway System: Provincial Trunk Highway 6 Twinning and Passing Lanes

Rosser, Manitoba

completeHighways and RoadsNRP
Federal contribution
$6.8M
$6,760,000
Federal share44%

of $15.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2019
2018202020222024
Built

Approved 11 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Jun 1, 2022(actual)
Construction end
Jun 14, 2024(actual)

Against the original forecast

  • Construction start3 months earlyforecast Aug 31, 2022
  • Construction end2 weeks earlyforecast Jun 30, 2024

Also in Rosser

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51889 in the federal list. How to read these figures.