Back to projects

Du Lac-Vert Concession Road Resurfacing

Hébertville, Quebec

completeHighways and RoadsISF
Federal contribution
$1.1M
$1,123,513
Federal share40%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
May 10, 2010(actual)
Construction end
Sep 22, 2011(actual)

Against the original forecast

  • Construction start8 months lateforecast Sep 1, 2009
  • Construction end3 weeks lateforecast Aug 31, 2011

Also in Hébertville