Back to projects

Rebuilding the Intersection of Route 169 and Martin Street in Hébertville

Hébertville, Quebec

completeHighways and RoadsISF
Federal contribution
$1.0M
$1,033,000
Federal share50%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Aug 13, 2010(actual)
Construction end
Jul 14, 2011(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 15, 2010
  • Construction end7 weeks earlyforecast Aug 31, 2011

Also in Hébertville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34713 in the federal list. How to read these figures.