Rebuilding the Intersection of Route 169 and Martin Street in Hébertville
Federal contribution
$1.0M
$1,033,000
Federal share50%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Aug 13, 2010(actual)
- Construction end
- Jul 14, 2011(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jun 15, 2010
- Construction end7 weeks earlyforecast Aug 31, 2011
Also in Hébertville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34713 in the federal list. How to read these figures.