Repaving Highway 30
Federal contribution
$1.2M
$1,158,285
Federal share38%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 27, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Jul 29, 2010(actual)
- Construction end
- Aug 31, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jul 1, 2010
- Construction end2 months earlyforecast Oct 31, 2011
Also in Brossard
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29261 in the federal list. How to read these figures.