Repairs to Highway 30 West

Brossard, Quebec

completeHighways and RoadsISF
Federal contribution
$873,562
Federal share35%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 13, 2009
ApprovedJan 26, 2010
2010
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Aug 2, 2010(actual)
Construction end
Oct 20, 2010(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 1, 2010