Underground Utility Corridor Repair for the Town of Norman Wells
Norman Wells, Northwest Territories
Federal contribution
$228,035
Federal share29%
of $800.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 11, 2009
2010
Built
Approved 4 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Norman Wells
- Construction start
- Mar 1, 2010(actual)
- Construction end
- Sep 30, 2010(actual)
Against the original forecast
- Construction start4 months earlyforecast Jul 1, 2010
- Construction end3 months earlyforecast Dec 31, 2010