Kusawa Lake Road Reconstruction
Federal contribution
$21,000
Federal share50%
of $42.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 13, 2009
ApprovedJan 28, 2010
2010
Built
Approved 9 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Yukon
- Construction start
- May 19, 2009(actual)
- Construction end
- Aug 31, 2009(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Jul 1, 2009
Also in Whitehorse
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29291 in the federal list. How to read these figures.