Forest Service Roads Improvements - Seymour Arm
Federal contribution
$499,305
Federal share50%
of $998.6K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 7, 2009
ApprovedJan 28, 2010
2010
Built
Approved 10 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Sep 18, 2009(actual)
- Construction end
- Jun 30, 2010(actual)
Against the original forecast
- Construction start6 months lateforecast Apr 1, 2009
Also in Seymour Arm
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29306 in the federal list. How to read these figures.