Upgrades to Adams West Forest Service Road

Seymour Arm, British Columbia

completeHighways and RoadsISF
Federal contribution
$500,000
Federal share50%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedJan 28, 2010
2010
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jul 21, 2009(actual)
Construction end
Jun 30, 2010(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2009