Back to projects

Sidewalks and Pathway

Vernon, British Columbia

completeHighways and RoadsISF
Federal contribution
$266,906
Federal share25%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedAug 10, 2009
20102011
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vernon
Construction start
Nov 15, 2009(actual)
Construction end
Dec 30, 2010(actual)

Against the original forecast

  • Construction start5 months lateforecast Jul 1, 2009
  • Construction end6 months lateforecast Jun 30, 2010

Also in Vernon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29343 in the federal list. How to read these figures.