Shuswap Avenue Pathway
Federal contribution
$57,533
Federal share25%
of $230.1K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedAug 10, 2009
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Village of Lumby
- Construction start
- Jul 23, 2009(actual)
- Construction end
- Sep 9, 2009(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 1, 2009
- Construction end7 months earlyforecast Mar 31, 2010
Also in Lumby
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29389 in the federal list. How to read these figures.