Shuswap Avenue Pathway

Lumby, British Columbia

completeActive TransportationISF
Federal contribution
$57,533
Federal share25%

of $230.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedAug 10, 2009
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Village of Lumby
Construction start
Jul 23, 2009(actual)
Construction end
Sep 9, 2009(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 1, 2009
  • Construction end7 months earlyforecast Mar 31, 2010

Also in Lumby

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29389 in the federal list. How to read these figures.