Lumby Community Park Lift Station Replacement and Amenity Upgrade
Federal contribution
$519,333
Federal share33%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 10, 2015
2016
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Lumby
- Construction start
- Nov 20, 2015(actual)
- Construction end
- Nov 4, 2016(actual)
Against the original forecast
- Construction start7 weeks lateforecast Oct 1, 2015
- Construction end4 weeks earlyforecast Nov 30, 2016