Long-Term Wastewater Treatment Plant Upgrades

Lumby, British Columbia

completeWastewaterCWWF
Federal contribution
$119,559
Federal share50%

of $239.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Lumby
Construction start
Sep 20, 2017(actual)
Construction end
Mar 27, 2020(actual)

Against the original forecast

  • Construction start7 months lateforecast Mar 1, 2017