Resurfacing of Asphalt on Highway 15

Sainte-Agathe-des-Monts, Quebec

completeHighways and RoadsISF
Federal contribution
$1.3M
$1,323,563
Federal share44%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
2010
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Jul 5, 2010(actual)
Construction end
Sep 20, 2010(actual)

Also in Sainte-Agathe-des-Monts

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29455 in the federal list. How to read these figures.