Renewal of water pipes

Sainte-Agathe-des-Monts, Quebec

completeDrinking WaterCWWF
Federal contribution
$524,240
Federal share50%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 3, 2017
Built

Approved 2 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
May 23, 2017(actual)
Construction end
Sep 5, 2017(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 1, 2017
  • Construction end7 months earlyforecast Mar 31, 2018