Pumping System Repairs

Montréal, Quebec

completeHighways and RoadsISF
Federal contribution
$2.1M
$2,063,019
Federal share38%

of $5.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
2010201120122013
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Dec 10, 2010(actual)
Construction end
Apr 30, 2013(actual)

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29472 in the federal list. How to read these figures.