Maison de la culture Francis Brisson
Federal contribution
$1.2M
$1,161,310
Federal share31%
of $3.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 28, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Shawinigan
- Construction start
- Mar 10, 2011(actual)
- Construction end
- Oct 31, 2011(actual)
Also in Shawinigan