Trans-Canada Highway - Paving from 20 Kilometres West of Highway 5 to Highway 5
Federal contribution
$5.1M
$5,128,894
Federal share46%
of $11.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 22, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Manitoba
- Construction start
- May 10, 2010(actual)
- Construction end
- Sep 27, 2011(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Jun 1, 2010
- Construction end4 weeks lateforecast Aug 31, 2011