Back to projects

Town of Carberry Lagoon Expansion

Carberry, Manitoba

approvedWastewaterGIS
Federal contribution
$3.1M
$3,063,600
Federal share40%

of $7.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2022
today
2022202420262028
BuiltForecast

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Carberry
Construction start
Jun 1, 2026(forecast)
Construction end
Oct 31, 2027(forecast)

Also in Carberry