Highway 1 East Reconstruction, from Highway 100 to Highway 12
Federal contribution
$28.9M
$28,938,016
Federal share50%
of $58.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 22, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Manitoba
- Construction start
- Jun 9, 2009(actual)
- Construction end
- Mar 24, 2011(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Jul 1, 2009
Also in Taché
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29533 in the federal list. How to read these figures.