Landmark Water Utility Upgrade

Taché, Manitoba

completeDrinking WaterSCF
Federal contribution
$1.2M
$1,200,000
Federal share33%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
20162017201820192020
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Aug 17, 2018(actual)
Construction end
Dec 18, 2019(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jul 30, 2018

Also in Taché

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46332 in the federal list. How to read these figures.