Schedule

AnnouncedMar 13, 2009
ApprovedAug 10, 2009
20102011
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Grand Forks
Construction start
Aug 3, 2010(actual)
Construction end
Sep 16, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2010
  • Construction end6 weeks earlyforecast Oct 31, 2011

Also in Grand Forks