Wastewater Treatment Plant (WWTP) Ultra-Violet Disinfection

Grand Forks, British Columbia

completeWastewaterSCF
Federal contribution
$213,333
Federal share33%

of $640.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 10, 2015
201620172018201920202021
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Grand Forks
Construction start
Jul 2, 2019(actual)
Construction end
Mar 1, 2021(actual)

Against the original forecast

  • Construction start2 months lateforecast May 1, 2019
  • Construction end9 months lateforecast Jun 1, 2020