Road Construction of Rural Road 36
Federal contribution
$127,878
Federal share33%
of $383.7K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedJan 27, 2010
2010
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Sep 25, 2009(actual)
- Construction end
- Dec 31, 2009(actual)
Against the original forecast
- Construction start2 months lateforecast Jul 15, 2009
- Construction end7 weeks lateforecast Nov 15, 2009
Also in Cymri No. 36
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29637 in the federal list. How to read these figures.