Terminal Road Paving

Cymri No. 36, Saskatchewan

completeHighways and RoadsSCF
Federal contribution
$1.2M
$1,204,646
Federal share33%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2018
2019
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Dec 1, 2018(actual)
Construction end
Nov 17, 2019(actual)

Against the original forecast

  • Construction start4 months lateforecast Aug 1, 2018
  • Construction end6 weeks earlyforecast Dec 31, 2019

Also in Cymri No. 36

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52568 in the federal list. How to read these figures.