Extension of Berths at Docks 76 and 77
Federal contribution
$5.1M
$5,100,000
Federal share50%
of $10.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 4, 2010
2011
Built
Approved 2 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Montreal Port Authority
- Construction start
- Jun 7, 2010(actual)
- Construction end
- Sep 30, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast May 15, 2010
- Construction end4 weeks lateforecast Aug 31, 2011
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29668 in the federal list. How to read these figures.