Asphalt Resurfacing of Highway 20
Federal contribution
$1.5M
$1,498,050
Federal share26%
of $5.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 27, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- May 24, 2011(actual)
- Construction end
- Jul 8, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast May 1, 2011
- Construction end4 months earlyforecast Oct 31, 2011