Back to projects

Asphalt Resurfacing of Highway 20

Montréal, Quebec

completeHighways and RoadsISF
Federal contribution
$1.5M
$1,498,050
Federal share26%

of $5.7M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
May 24, 2011(actual)
Construction end
Jul 8, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 1, 2011
  • Construction end4 months earlyforecast Oct 31, 2011

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29699 in the federal list. How to read these figures.