Ramp Resurfacing Projects on Highway 50

Gatineau, Quebec

completeHighways and RoadsISF
Federal contribution
$1.5M
$1,500,000
Federal share50%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
2010
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
May 15, 2010(actual)
Construction end
Aug 19, 2010(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Jun 1, 2010
  • Construction end2 months earlyforecast Oct 31, 2010