Lenchuk Creek bridge replacement

Reynolds, Manitoba

completeHighways and RoadsISF
Federal contribution
$75,437
Federal share30%

of $250.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 11, 2009
ApprovedJan 26, 2010
2010
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Sep 10, 2010(actual)
Construction end
Oct 22, 2010(actual)

Also in Reynolds