Back to projects

Medika Drain Rehabilitation Phase 3

Reynolds, Manitoba

completeDisaster MitigationSCF
Federal contribution
$45,289
Federal share30%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 9, 2017
201820192020
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Aug 26, 2019(actual)
Construction end
Aug 24, 2020(actual)

Also in Reynolds