Schedule

Announced and approvedFeb 21, 2011
20102011201220132014
Built

Approved 16 months before the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Ultimate recipient
Province of Alberta
Construction start
Oct 15, 2011(actual)
Construction end
Jun 30, 2014(actual)

Against the original forecast

  • Construction start3 months lateforecast Jul 20, 2011
  • Construction end6 months earlyforecast Dec 31, 2014