Regional Municipality of Wood Buffalo -Lower Townsite Flood Mitigation (Reach 7 and 8)
Wood Buffalo (Regional Municiaplity), Alberta
Federal contribution
$3.5M
$3,451,996
Federal share40%
of $8.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 2, 2020
202120222023
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Regional Municipality of Wood Buffalo
- Construction start
- May 17, 2021(actual)
- Construction end
- Oct 10, 2023(actual)
Against the original forecast
- Construction end3 months earlyforecast Dec 31, 2023
Also in Wood Buffalo (Regional Municiaplity)
- Thickwood Boulevard Interchange and Confederation Way Interchange on Highway 63$40.0M
- The Fort McMurray Metis Cultural Centre$16.5M
- Widening of Highway 63 from Morrison Street to the Athabasca River Bridge$8.5M
- Fort McMurray International Airport Expansion$6.0M
- Fort Chipewyan Six Bay Garage & Animal Control Facility, Phase 2$4.3M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56631 in the federal list. How to read these figures.