Regional Municipality of Wood Buffalo -Lower Townsite Flood Mitigation (Reach 7 and 8)

Wood Buffalo (Regional Municiaplity), Alberta

completeDisaster MitigationGIS
Federal contribution
$3.5M
$3,451,996
Federal share40%

of $8.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 2, 2020
202120222023
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Construction start
May 17, 2021(actual)
Construction end
Oct 10, 2023(actual)

Against the original forecast

  • Construction end3 months earlyforecast Dec 31, 2023