Mount Royal University Conservatory and Performance Hall
Federal contribution
$20.0M
$20,000,000
Federal share28%
of $72.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 16, 2010
201020112012201320142015
Built
Approved 7 months before the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- The Board of Governors of Mount Royal University
- Construction start
- Nov 19, 2012(actual)
- Construction end
- Aug 28, 2015(actual)
Against the original forecast
- Construction end2 months lateforecast Jun 25, 2015
Also in Calgary
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29840 in the federal list. How to read these figures.