Highway 1: Monte Creek to Pritchard

Pritchard, British Columbia

completeHighways and RoadsMIC
Federal contribution
$16.7M
$16,700,000
Federal share50%

of $33.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 30, 2008
2009201120132015
Built

Approved 8 weeks before the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Construction start
Oct 4, 2011(actual)
Construction end
Jul 31, 2015(actual)

Against the original forecast

  • Construction start14 months lateforecast Jul 23, 2010
  • Construction end4 months earlyforecast Nov 30, 2015

Also in Pritchard

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29844 in the federal list. How to read these figures.