Back to projects

Highway 1: Pritchard to Hoffman's Bluff and Hoffman's Bluff

Pritchard, British Columbia

completeHighways and RoadsMIC
Federal contribution
$23.8M
$23,848,277
Federal share48%

of $50.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 23, 2010
20092011201320152017
Built

Approved 15 months before the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Construction start
Jul 17, 2013(actual)
Construction end
Mar 15, 2017(actual)

Against the original forecast

  • Construction start3 years lateforecast Jul 23, 2010
  • Construction end7 months lateforecast Jul 31, 2016

Also in Pritchard

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29846 in the federal list. How to read these figures.